Kinson Primary School

mf7Project: Classroom building

Client: Kinson School

Completed: November 2016

Floor Area: 150m²

Duration: 5 Weeks

Value: £130,000

Turnkey service elements completed:

  • Design
  • Groundworks
  • Manufacture
  • Installation
  • Service Connections
  • Access Facilities

Kinson Primary Schol had a need for a Primary school kitchen, classroom and the main hall building to fit their budget and time constraints. Modulek project managed the build from its initial concept to completion, providing the school with a building that they can be proud of. This unique building is

This unique building has used hybrid methods of construction as it is half modular and half traditional steel frame. Another key feature of this state of the art building is the natural ventilation ECO stuck system to the hall. This system naturally ventilates the hall without the need of mechanical pumps and further equipment. This provides an environmentally friendly solution which is more economical when compared to the traditional methods.

Modulek offered a turnkey solution to include all groundworks, modular installation and finishing, traditional steel frame hall, ramps, paths steps, drainage, gas & electricity supply, facing brickwork and interior fit out.