Beech Hall School

mf7Client: Beech Hall School
Project: DT Room, Science Lab and Changing Facility
Completed: August 2019
Floor area: 10 modules
Value: £658,000

Turnkey service elements completed:

  • Demolition
  • Groundworks
  • Design
  • Manufacture
  • Delivery
  • Installation
  • Internal fit out and finishing
  • Service Connections
  • Brick & Tarmac Work
  • Flooring

This project started with the demolition of the existing building. The oversite was then prepared to receive a piled foundation with 99 individual piles and a perimeter groundbeam.

New gas and water mains were ran 60m in trenches to the new building. 10 modules were installed in a single day after a complex delivery procedure involving an additional mobile crane and an off-site vehicle change location to negotiate the extremely difficult access.

Specialist equipment for science labs and design technology rooms was installed. Brickwork exterior skin was constructed on top of new groundbeam, new tarmac footpath and tarmac repair works to existing driveway. Building finished with bifold doors and anti-slip decking.